Recommended Launch Path
August 1 Lean
The strongest balance of scope, timing, and recovery room.
Recommended Launch Path
The strongest balance of scope, timing, and recovery room.
Earliest Likely First Sail
The earliest realistic in-water target in the current plan set.
Built-In Schedule Buffer
The lean-scope options keep six recoverable dry-window days.
Project Photo Count
Project photos currently published from the Hydrotherapy build log.
Open project photosLaunch Options
The current planning package compares two target launch dates and two levels of work scope. Lean scope protects breathing room. Expanded scope uses up more of the yard window and leaves less room for surprises.
Best balance of finish quality, prep time, and schedule buffer.
Fastest workable route to the water if prep and paint stay clean.
Broader work package, but no dry-window buffer once it starts.
Most aggressive path: full scope, fixed date, and almost no room for surprises.
Working Schedule
These schedule views show what has to happen first, what work sits on the critical path, and where each launch date is most exposed to delay.
The strongest overall balance between realism, procurement time, and recoverable float before splash day.
Jun 1 to Jun 6
Dry access starts with the must-finish systems work: through valves, hose condition, and anything hidden behind backing plates.
Jun 7 to Jun 26
Wash, dewax, sand, mask, then prime and touch up the surfaces that reveal themselves during prep.
Jun 27 to Jul 13
Topcoat, nonskid, cockpit repaint, and cure time all live here. Weather is the biggest variable in this stretch.
Jul 14 to Jul 25
Fit the new rudder and tiller, then close out the dry-side work so launch prep is not being done in a panic.
Aug 2 to Aug 9
Gate valves, electrical proving, dockside checks, readiness review, then the earliest realistic first sail.
The fastest realistic route to the water if the paint sequence stays disciplined and the prep phase does not sprawl.
May 17 to May 22
The July clock starts moving immediately with the dry-only systems work that cannot be pushed later.
May 23 to Jun 11
Deck prep, primer, touch-ups, and cure all stack tightly, which means sanding cleanup and weather both matter.
Jun 12 to Jun 28
This is the most weather-sensitive stretch, and it has to settle before the fit-up work can move confidently.
Jun 29 to Jul 10
The boat needs the steering hardware sorted and the launch prep wrapped before the fixed splash date.
Jul 18 to Jul 25
Gate valves and electrical work run after launch, followed by dockside tests and the earliest realistic first sail.
The most realistic expanded-scope version, but it still uses the full dry window and leaves no recovery days before launch.
Jun 1 to Jun 10
The expanded path begins with extra disassembly before the core systems work, which creates more dependencies later.
Jun 11 to Jul 1
Prep expands to cover more surfaces, and local fairing is allowed where prep reveals issues.
Jul 2 to Jul 23
The finish sequence is longer here, and cure timing becomes the schedule gate before rebedding can start.
Jul 24 to Jul 31
Critical deck hardware goes back on, then the rudder and tiller are fitted at the end of the dry window.
Aug 2 to Aug 11
Electrical proving, valve work, extra safety setup, and dockside checks extend the gap between splash day and sailing.
The most aggressive scenario on the board: full dry-window usage, added scope, and no recovery days if anything runs long.
May 17 to May 26
Hardware removal and through valves start immediately, leaving very little slack for hidden damage.
May 27 to Jun 16
Deck and cockpit prep, followed by spot repairs, carry the highest chance of revealing time-consuming surprises.
Jun 17 to Jul 8
Every weather interruption here squeezes the rest of the schedule because there is no extra dry time left at the end.
Jul 9 to Jul 16
The final week stacks rebedding, fit-up, and launch readiness together with no margin for rework.
Jul 18 to Jul 27
Electrical, safety checks, and readiness review all happen after launch, so the first sail only happens if nothing snags.
Where The Schedule Gets Tight
Planning snapshot from the current Hydrotherapy schedule package.
Current Project Status
These updates are meant to help someone new understand the build quickly: what work is active now, what stage comes next, and what changes actually affect the launch target.
The marks, cutouts, and opened sections in the progress photos show where damaged material is being taken out so the structure can be rebuilt properly before fairing, paint, and reassembly begin.
That means cleaning back damaged areas, making sure the surfaces are ready to bond properly, and then moving into the fiberglass work that restores strength before fairing, paint, and reassembly.
Some images show the goal, some show the grind, and together they explain why certain dates feel solid while others are still stretch targets.
Featured Gallery
Click any image to enlarge it. This section keeps the Hydro page focused on the latest visual progress instead of showing the full archive all at once.